Construction Lenders and Developers Cannot Agree on Draw Package Standards, and It Is Costing Both Sides




Construction lenders and developers are locked in a prolonged dispute over draw package standards, with each side blaming the other for the lack of progress. Both say they want standardized draw package formats to streamline funding requests, yet neither has moved to resolve the deadlock.
Will Mitchell, Co-Founder and CEO of Rabbet, a construction finance software platform, sees the draw package standoff play out regularly. “Lenders will say they tell developers what format they want, but the developers won’t change,” Mitchell says. “Then you talk to developers, and they say they wish lenders would just tell them what format to use so they can comply.”
The draw package standoff points to a deeper problem: there is no industry-wide agreement on what a standard draw package should look like. Without consensus, every transaction requires custom negotiation, manual workarounds, and redundant documentation. The resulting inefficiencies slow project timelines and increase administrative costs.
How Inconsistent Draw Package Formats Slow Construction Funding and Raise Costs
Draw packages, the documentation that developers submit to lenders to request construction funding disbursements, vary widely in format, structure, and content requirements across lenders. The absence of a consistent standard forces developers to customize submissions for each lender relationship. At the same time, lenders must review packages in inconsistent formats, making approval more complex and time-consuming.
Mitchell argues that format variability across lenders creates unnecessary friction in what should be a routine administrative process, and that a broadly accepted standard would allow both parties to transact more efficiently.
The problem is especially pronounced for developers working with multiple lenders on different projects. Those developers must maintain separate documentation systems for each lender relationship. Lenders, meanwhile, process draw requests from various developers using different structures. That inconsistency makes it difficult to implement standard review procedures or automate parts of the approval process.
Despite the construction finance industry’s adoption of digital tools for project management and accounting, inconsistent draw package formats remain a significant gap. Mitchell points out that the issue is not a lack of technology, since most participants have access to software that could support standardization, but rather the absence of agreement on what the standard should be.
Why the Construction Finance Industry Has Failed to Agree on a Draw Package Standard
In other industries, large players or industry associations often set de facto standards that smaller participants follow. Construction finance has not produced such a standard, despite clear efficiency gains available to both lenders and developers.
Mitchell observes that lenders believe they are communicating requirements clearly, while developers claim not to receive clear guidance. This gap suggests the problem goes beyond non-compliance. In many cases, lenders may impose requirements that are too vague or overly tailored to their internal systems, making those requirements impractical as a broader standard.
Developers may receive format guidance from lenders but find the requirements difficult to apply consistently across multiple lender relationships. Conflicts between lender requirements compound the problem. Faced with incompatible demands, developers may default to their own internal formats and hope lenders will accept those submissions, rather than maintain multiple parallel documentation systems.
The conflict between incompatible requirements has produced a stalemate in which both sides express frustration but neither has enough incentive or authority to drive industry-wide change.
How One Construction Finance Platform Is Trying to Resolve the Draw Package Standoff
Rabbet is working to resolve the draw package standoff directly. “We’re working on a project to help lenders and developers agree on a format for transferring draw packages,” Mitchell says. The firm’s approach is to build a common format within its platform that both lenders and developers can adopt.
If the common format gains traction within Rabbet’s platform, it could serve as a proof of concept for broader adoption and establish a de facto standard that other software providers and market participants follow.
Mitchell says standardizing draw package formats aligns with Rabbet’s broader goal of helping industry participants transact more efficiently and use data more effectively. Standardized formats would also allow for better data aggregation, benchmarking, and analysis across projects, benefits that extend beyond administrative streamlining.
Rabbet serves both lenders and developers, giving the platform direct visibility into each side’s requirements. According to Mitchell, the platform has “about the same amount of users on both sides of the ecosystem,” which may give Rabbet enough influence to drive adoption of a common standard among its existing users.
Whether Rabbet’s common format initiative can expand beyond its existing customers to become an industry-wide standard remains uncertain. Mitchell acknowledges that broader adoption will require buy-in beyond what any single software platform can deliver, even as he sees standardizing drawing package formats as a significant opportunity for the industry.
Why the Draw Package Problem Persists Despite the Technology to Fix It
For now, inconsistent draw package formats continue to generate costly delays in construction finance. Both lenders and developers lose time and money to redundant paperwork and formatting disputes, even though the technology to resolve them exists.
The ongoing lack of consensus, rather than any technical barrier, remains the main reason the construction finance industry still lacks a standard draw package format. Until industry participants agree on a shared approach, each new project will face the same administrative hurdles, adding time and cost that standardization could eliminate.
Standardization could deliver significant efficiency gains for lenders and developers alike, but without collective action from the industry, the draw package standoff will continue to slow construction finance and add avoidable cost to every project.
This article was sourced from a live expert interview.
Every month we conduct hundreds of interviews with
active market practitioners - thousands to date.
Similar Articles
Explore similar articles from Our Team of Experts.


The real estate industry is approaching a technological tipping point that will force many agents out of the business, according to Cyrus Mohseni, Co-Founder & Vice President of Strategy...


What started as an effort to democratize iBuying for real estate agents has evolved into a rapidly growing FinTech platform serving real estate investors. homebldr, founded in February 2021,...


The real estate brokerage industry is under increasing pressure to reduce costs while maintaining high service standards. As physical office spaces become more expensive and competition grow...


Most homeowners know the basics of property ownership, pay the mortgage, mow the lawn, and call a professional when something breaks. But as fewer people learn hands-on maintenance skills, a...