KeyCrew Journal Logo

How Long Does a Simple Commercial Building Permit Really Take in Phoenix, Arizona?

Written by:
Date:
19 Nov 2026
Share

Business owners planning a tenant improvement in Phoenix, Arizona often hear that a commercial building permit takes about 30 days. That number is a reasonable place to start, but it rarely reflects the full time between deciding to submit plans and holding an approved permit.

Mike Marden, a registered architect and licensed general contractor who founded WDS, a Phoenix-based integrated design-build firm, says owners are usually caught off guard by the steps around the city’s review rather than the review itself. Most of those steps never appear in a published timeline.

Why “30 Days” Depends on Where Your Project Is

Mike says 30 days is the default his firm works from for the first review of a typical tenant improvement permit. From there, the answer depends on which city is reviewing the plans. The Phoenix area has roughly 20 municipalities, and WDS works regularly in six to eight of them. Each one publishes its review cycles a little differently.

Some list calendar days. Others count business days, and some city offices are only open Monday through Thursday. That difference adds up quickly. A review published as 27 business days at a city that does not work Fridays can stretch to five or six weeks on the calendar.

Because of that, Mike says his team plans around the published worst case. On one recent project, the clients were taken aback by the timeline the city had posted. The review did not end up taking as long as planned, but there was no way to know that in advance, and the schedule had to reflect what the city put in writing to protect both WDS and the client.

The Steps That Aren’t in the Published Timeline

The bigger gap, according to Mike, is that a published review period usually covers only the technical review. Two other steps happen around it, and owners rarely hear about either one.

The first is preparing the submittal. Most municipalities mandate that plans be submitted online via the city’s public portal, and each has its own rules for how files are organized. Some want each discipline uploaded separately, others want individual sheets broken out, and some let applicants save an application in progress while others require it to be completed in one sitting. Mike says this preparation can take as much as several days, depending on whether an account has been set up.

The second is an administrative review. Before plans go to technical reviewers, city technicians check whether the submittal is complete. “They’ll look at what’s been uploaded and send notification by email that you’re missing a form, or that they think you should have this other item on your plan,” Mike says. That check can take anywhere from three to 15 days, and it is generally not counted in the review time the city publishes. Only after it clears does the three- or five-week technical review actually begin.

Where Owners Can Actually Save Time

Once plans are in the city’s hands, there is little an owner can do to speed up the review. Mike says the real time savings come earlier, during design, and they depend largely on how quickly owners provide information and make decisions.

He describes a situation his team works to avoid when choosing clients. In one ear, the owner is asking how soon the plans can be submitted and why they haven’t been yet. In the other, the same owner is leaving requests for design input unanswered.

“Showing up ready to make decisions and getting us the information helps us get into the city process faster,” Mike says. Owners who follow the design team’s process and complete their action items on time move into city review sooner than those who are still deciding.

How Choosing a Contractor Affects the Permit

Mike also points to a gap that has nothing to do with the city: the time between getting plans approved and deciding who will build the project.

Some owners rush to submit plans and then start looking for a general contractor while the review is underway, or after it is complete. If bids come back higher than expected, the owner may want to change the design. Revisions extend the review, and if the changes are significant enough, the city can require the submittal to start over.

There is also a requirement many owners don’t know about. For a commercial project, the city will not release the permit until the owner names a licensed general contractor, and since it is not a residential permit, that contractor must list a proper commercial license. An owner who hasn’t selected a contractor by then may go through a 30-day bid cycle while an approved permit sits waiting, and while lease or mortgage payments continue on a space that can’t be built out yet.

This is one reason Mike’s firm keeps design and construction on the same team, with plans prepared through WDS Architecture and costs reviewed as the design develops. When pricing is known along the way, owners are less likely to face a late redesign, and the permit can be released as soon as it is approved.

There are other strategies that can be discussed further but fall outside the focus of this article. They include choosing a business-friendly jurisdiction in which to locate the project, beginning certain construction-related activities before the permit is issued, and using one of a few expedited, self-certified, or permit-by-inspection programs, which are real but very rare.

For owners planning a buildout in the Phoenix area, Mike’s advice is to build these steps into the schedule from the start: plan for the published worst case, allow time for submittal prep and administrative review, and have a contractor in place before the permit is ready to be issued.


WDS is an integrated design-build firm based in Phoenix, Arizona, comprised of WDS Architecture PLLC and WDS Commercial LLC, subsidiaries of Marden Companies LLC.

This article is based on information provided by the expert source cited above. It is intended for general informational purposes only and does not constitute legal, financial, or real estate advice. Readers should conduct their own research and consult qualified professionals before making any real estate or financial decisions.

Disclosure: Individuals or companies mentioned may have a commercial relationship with KeyCrew.